Solid and liquid contaminants site risk assessments
Contaminated land is land that presents a hazard in the form of material that has the potential for harm. Assessment of the risk of harm is based on the likelihood, frequency and seriousness of the adverse consequences of contaminants. See contaminated land for more information.
Where development sites are affected by solid or liquid contaminants, Approved document C, Site preparation and resistance to contaminants and moisture, suggests that the principles of risk assessment should follow the ‘source–pathway–receptor’ relationship, or 'pollutant linkage', where:
- ‘Sources’ are contaminants in or on the ground.
- ‘Receptors’ are the buildings, building materials, building services and people introduced onto the site.
- ‘Pathways’ are the pollutant linkages between sources and receptors which must be broken or conditioned so they do not pose a significant risk.
The approved document suggests that this can be achieved by:
- Treating the contaminant. The use of physical, chemical or biological processes to eliminate or reduce the contaminant’s toxicity or harmful properties.
- Blocking or removing the pathway. Isolating the contaminant beneath protective layers or installing barriers to prevent migration.
- Protecting or removing the receptor. Changing the form or layout of the development, using appropriately designed building materials.
- Removing the contaminant.
The assessment of risk should adopt a tiered approach. A preliminary risk assessment should be undertaken, and depending on the outcome, either a generic quantitative risk assessment (GQRA) or detailed quantitative risk assessment (DQRA), or both, may be necessary.
CLR 11 Model Procedures for the Management of Land Contamination, Defra/Environment Agency, 2004 suggests that the stages of risk assessment should be:
- Hazard identification (the preliminary site assessment). A desk study and site walkover to establish contaminant sources, pathways and receptors and to design exploratory and detailed ground investigations.
- Hazard assessment. Identify linkages and the potential for unacceptable risks and undertake exploratory site investigation.
- Risk estimation. Assess the degree of harm that may result to which receptors and undertake detailed ground investigation
- Risk evaluation. Consider whether the risks are acceptable.
If unacceptable risks to a receptor are identified, remedial measures must be used to break the pollutant linkages.
Depending on the contaminant, three types of remedial measures can be considered:
- Treatment.
- Containment.
- Removal.
Treatment may include biological, chemical and physical techniques carried out on or off site to decrease the mass, concentration, mobility, flux or toxicity of contaminants.
Containment generally involves encapsulation of material containing contaminants or the use of cover systems, placing one or more layers of materials over the site to: break the pollutant linkage, sustain vegetation, improve geotechnical properties, and reduce exposure to an acceptable level. Vertical barriers may also be required to control lateral migration of contaminants. Maintenance and monitoring may be necessary to ensure integrity from burrowing animals, gardening, excavations by householders and so on.
The containment or treatment of waste may require a waste management licence from the Environment Agency.
Removal involves the excavation and disposal to of contaminants to licensed landfill sites.
[edit] Related articles on Designing Buildings Wiki
- Brownfield land.
- Building on fill.
- Conceptual site model.
- Contaminated land.
- Cover systems for land regeneration - thickness of cover systems for contaminated land (BR465).
- Deleterious materials.
- Designing to reduce the chemical, biological and radiological vulnerability of new buildings (IP 7/15).
- Diffuse pollution.
- Ground conditions.
- Methane and other gasses from the ground.
- Pollution.
- Radon.
- Radon: Guidance on protective measures for new buildings BR 211.
- Radon protection for new domestic extensions and conservatories with solid concrete ground floors (GG 73 revised).
- Site appraisal.
- Site investigation.
- Soil survey.
[edit] External references
- Guidelines for combined geoenvironmental and geotechnical investigations, Association of Geotechnical and Geoenvironmental Specialists.
- BS 5930:1999+A2:2010. Code of practice for site investigations.
- BS 10175:2011 Code of practice for investigation of potentially contaminated sites.
- Human health toxicological assessment of contaminants in soil (Science report – final SC050021/SR2), Environment Agency.
- Updated technical background to the CLEA model (Science Report: SC050021/SR3), Environment Agency.
- CLR 11. Model Procedures for the Management of Land Contamination. Defra/Environment Agency, 2004.
- Environment Agency R & D Technical Report P5-065 Technical aspects of site investigation, 2000.
- Environment Agency R & D Technical Report P5-066 Secondary model procedure for the development of appropriate soil sampling strategies for land contamination
Featured articles and news
New Great British Energy partnership launched
Crown estate help to turbocharge energy independence.
ECA Industry Awards 2024 shortlist revealed
22 leading businesses from across the electrotechnical and engineering services sector.
Government unveils Skills England strategy
Skills England to transform opportunities and drive growth.
New Government Hub for York Given Planning Green Light
For up to 2,600 civil servants, due for completion by 2028.
Construction Skills Certification Scheme cards
July update on Professionally Qualified and Academically Qualified Person Cards.
BSRIA Briefing 2024, November 22
Sustainable Futures: Redefining Retrofit for Net Zero Living.
The CLC on driving competency in the retrofit sector
Previously published roadmap on skills for net zero.
The first labour government King's speech in fifteen years
Construction industry reactions, support and some concern.
CIOB Retrofit of Buildings Technical Information Sheet
What retrofit is, the approach to be taken and processes to be followed.
Adapting Historic Buildings for Energy and Carbon Efficiency
Historic England advice note 18, free download published.
10 retrofit projects revisited 10 years after completion.
Information orders, building liability orders and SPVs
Key BSA terms and how they impact special purpose vehicles.
Listed despite problems with its design.
Zen and the art of cycling exploration.
Design Council Homes Taskforce launched
To support government 1.5 million homes target within UK climate commitments.